RESIDENTIAL CONSTRUCTION PROJECT IN HODDESDON, HERTFORDSHIRE FOR TAYLOR WIMPEY - HIGH LEIGH GARDEN VILLAGE
Project Description
90-unit project consisting of 72 houses and 18 flats with full infrastructure
Client: Taylor Wimpey
Start date: January 2025
Completion date: December 2026
Value: £7.2m
Project Details
- GPS controlled earthworks modelling, surcharging and stockpiling
- Last phase of multi-phase project total value £35m
- Piling platforms
- Piled foundations and ground beams
- Deep trench fill foundations
- Substructure brickwork and low U value PCC floors
- Private and adoptable SW and foul drainage
- Attenuation basins with headwalls and outfall into local brook
- Silt protection barriers
- Flow control manholes
- Adoptable carriageways
- Private carriageway, permeable and impermeable drives
- Private paths and patios extensive steps
- Tobermore Walls (retaining heights up to 4m)
- Reinforced concrete and masonry retaining walls
- POS hoggin footpaths
- Private and mains services with substation
- EV charging, streetlighting and connections

DOWNLOAD THIS PAGE AS A PDF
Download
TALK TO US ABOUT YOUR NEXT PROJECT
Contact Us


Residential Construction Project in Hoddesdon, Hertfordshire for Taylor Wimpey - High Leigh Garden Village
Residential Construction Project in Hoddesdon, Hertfordshire for Taylor Wimpey - High Leigh Garden Village

Residential Construction Project in Hoddesdon, Hertfordshire for Taylor Wimpey - High Leigh Garden Village